Summary
The EPA's Final Coal Combustion Residual (CCR) Rule was published on April 17, 2015 and went into effect on October 19, 2015. The rule regulates existing active CCR waste landfills and surface impoundments (ponds) and all new CCR waste disposal units built after the rule's publication. Tampa Electric's Big Bend Station has fulfilled all of its compliance obligations under the rule by closing and retrofitting all regulated CCR Units at the facility and has posted all relevant records related to these closure projects on this website.
TECO Big Bend CCR Rule Compliance Data and Information
- Economizer Ash Closure by Removal - 2021 Asbuilts - (Posted 06/20/23)
- Economizer Ash System - Closure Completion - (Posted 11/11/21)
- TECO Big Bend CCR Annual Report 2020 - (Posted 01/27/21)
- TECO Big Bend Coalfield Pond Closure Certification 2021 - (Posted 01/08/21)
- TECO Big Bend Eapp Annual Report 2019 - (Posted 01/23/20)
- Economizer Ash CCR Closure Temp Ditch Crossing Hydrology Report - (Posted 07/26/19)
- Economizer Ash CCR Closure Temp Ditch Crossing Plans - (Posted 07/26/19)
- Ash Ponds Detection Monitoring Report (Baseline) - (Posted 07/15/19)
- Ash Ponds Detection Monitoring Report 4 - (Posted 07/15/19)
- Ash Ponds Detection Monitoring Report 3 - (Posted 07/15/19)
- Ash Ponds Closure Specifications - (Posted 04/02/19)
- Ash Ponds Closure Plan Drawings - (Posted 04/02/19)
- Ash Ponds System CCR Impoundment Inspection Report - 2018 - (Posted 02/28/19)
- Ash Ponds System CCR Impoundment Inspection Report - 2017 - (Posted 02/28/19)
- Ash Ponds Annual GW Report - 2018 - (Posted 01/22/19)
- Ash Ponds Detection Monitoring Report 2 - (Posted 01/10/19)
- Slag Pond Closure Plan - (Posted 10/03/18)
- Ash Ponds Ash Closure Plan - (Posted 10/03/18)
- Ash Ponds Alternate Source Demonstration (ASD) - (Posted 04/17/18)
- Ash Ponds Certification of Alternate Source Demonstration - (Posted 04/17/18)
- Ash Ponds Annual GW Report - (Posted 02/06/18)
- GW Monitoring System Design and Construction Report - 2017 - (Posted 10/24/17)
- CCR Statistical Analysis Plan - 2017 - (Posted 10/24/17)
- Structural Stability Report CCR Economizer Ash System - 2017 - (Posted 5/26/17)
- Annual Berm Inspection Report - 2016 - (Posted 5/26/17)
- Ash and Slag Ponds Preliminary Closure Plan - (Posted 10/20/16)
- CCR Groundwater Monitoring Plan & Statistical Method Certification - (Posted 10/07/16)
- Ash Ponds System CCR Impoundment Inspection Report - 2015 - (Posted 02/05/16)
- CCR Fugitive Dust Control Plan - (Posted 11/3/15)